Project Scope This parking lot is a space for space replacement of the parking lot south of Browne Hall that will be lost during the construction of the Center for Performing Arts (CPA).
External Vendors Farnsworth Group for design and Laverdiere Construction for construction
Total Project Cost Approximately $1,048,000
Completion Date October 2014

Project Description

This parking lot is a space for space聽replacement of the parking lot south of聽Browne Hall that will be lost during the聽construction of the CPA. In addition to the聽new parking lot, new sidewalks, a bus stop,聽a bus turnout, and new lighting will be聽installed. Also, a masonry column to help聽define the corner of Western Avenue and聽Adams Street will be installed as an entrance聽to campus as well as an infrastructure for聽future electric vehicle charging stations.

Updates

As of October 28, 2014, the project is substantially complete.听